TC-06049-20 Pass UAT1 7/9/2025 9:59 AM 7/9/2025 9:59 AM Submitted for approval. PO was confirmed to have sent
TC-06049-02 Pass UAT1 7/2/2025 8:56 AM 7/2/2025 8:56 AM PO962 submitted for approval, now pending receipt. OM logistics set to pick up.
TC-06049-29 Pass UAT1 7/1/2025 8:54 AM 7/1/2025 8:54 AM PO963 updated and submitted for approval, now pending receipt.
TC-06049-23 Pass UAT1 6/16/2025 10:50 AM 6/16/2025 10:50 AM PO1181 submitted for approval now pending receipt.
TC-06049-28 Pass UAT1 6/10/2025 2:04 PM 6/10/2025 2:04 PM PO1104 submitted for approval and now pending receipt.
TC-06049-19 Pass UAT1 6/10/2025 10:56 AM 6/10/2025 10:56 AM PO1079 submitted for approval and now pending receipt.
TC-06049-13 Pass UAT1 6/10/2025 10:02 AM 6/10/2025 10:02 AM PO1077 submitted for approval, now pending receipt.
TC-06049-26 Pass UAT1 6/10/2025 8:22 AM 6/10/2025 8:22 AM PO1069 submitted for approval, now pending receipt.
TC-06049-25 Pass UAT1 6/9/2025 2:27 PM 6/9/2025 2:27 PM PO1066 submitted for approval, now pending receipt. Email Communication was sent to the Vendor/Supplie check box selected.
TC-06049-22 Pass UAT1 6/9/2025 1:01 PM 6/9/2025 1:01 PM PO1060 submitted for approval
TC-06049-21 Pass UAT1 6/9/2025 10:47 AM 6/9/2025 10:47 AM PO1058 submitted for approval, Email communication was sent to supplier check box selected on the communication tab.
TC-06049-10 Pass UAT1 6/9/2025 9:34 AM 6/9/2025 9:34 AM PO1051 OM logistics set to ship. Ship to address updated. Submitted for approval. PO confirmed checkbox selected after approval. Now in pending receipt status.
TC-06049-03 Pass UAT1 6/9/2025 8:40 AM 6/9/2025 8:40 AM PO added at header level after added to the service for purchase item.
TC-06049-11 Pass UAT1 6/6/2025 9:37 AM 6/6/2025 9:37 AM PO1053 OM logistics set to pick up. Ship to address updated. Submitted for approval. PO confirmed check box selected. PO in pending receipt status.
TC-06049-09 Pass UAT1 6/6/2025 8:53 AM 6/6/2025 8:53 AM PO1030 OM logistics set to ship. Ship to address updated. Submitted for approval. PO confirmed checkbox selected after approval. Now in pending receipt status.
TC-06049-08 Pass UAT1 6/6/2025 8:37 AM 6/6/2025 8:37 AM PO1029 - OM Logostics set for pick up. Ship to adress updated. Submitted for approval and now in pending receipt status.
TC-06049-07 Pass UAT1 6/6/2025 8:15 AM 6/6/2025 8:15 AM PO1028 OM logistics set to "at vendor." Ship to address updated and PO submitted for approval. In pending receipt status.
TC-06049-05 Pass UAT1 6/5/2025 2:01 PM 6/5/2025 2:01 PM PO1026 ship to address updated, PO released and is pending receipt.
TC-06049-06 Pass UAT1 6/5/2025 1:04 PM 6/5/2025 1:04 PM PO1023 submitted for approval. OM logistics defined.
TC-06049-04 Pass UAT1 6/5/2025 11:08 AM 6/5/2025 11:08 AM PO1018 updated and submitted for approval.
TC-06049-03 Fail UAT1 6/4/2025 1:19 PM 6/4/2025 1:19 PM Manual entry into the ship to address at the line level did not reflect in the ship to address at the header level, when the PO was saved.
TC-06049-01 Fail UAT1 6/3/2025 2:10 PM 6/3/2025 2:10 PM PO961 - Upon service PO review/approval, the "drawing#" and "revision#" did not populate.